T.v.Sunil v. the Kerala Agro-Industries Corporation Ltd.
Case brief
What is this about?
Petitioner, an empaneled contractor, sought payment of Rs.67,15,252/- for completed work. Court directed Respondent 1 to conduct Joint Inspection with petitioner's assistance and pay any found due within four months.
What did the court decide?
Directed Respondent 1 to complete Joint Inspection, take measurements expeditiously with petitioner's assistance, and pay the amount found due within four months.