M/S.Mariya Constructions, v. Kerala Water Authority
Case brief
What is this about?
A writ petition seeking an order for the payment of ₹23.08 lakhs due under a construction contract. The Kerala Water Authority cited financial crisis to delay payment. The court directed a 5-month deadline for the 3rd respondent to pay the amount, rejecting indefinite delay.
What did the court decide?
Directed the 3rd respondent to pay the undisputed bill amount of ₹23.08 lakhs to the petitioner within five months.