C.K.Mammen v. the Kerala Water Authority
Case brief
What is this about?
Petitioner sought foreclosure of a construction agreement and refund of deposited amounts due to delay caused by respondent's inaction in granting road-cutting permission. Court directed first respondent to consider petitioner's representation and pass orders after hearing.
What did the court decide?
Direct first respondent to consider petitioner's representation (Ext.P3) and pass orders within one month after giving opportunity of hearing.