The High Court disposed of a writ petition filed by a construction contractor seeking release of retained money and permission to foreclose a contract. The court recorded a tentative agreement between parties to modify payment terms and directed payment within three weeks.
What did the court decide?
Directing release of payable amount within three weeks and permitting parties to proceed with the contract under the agreed modified terms.