Monisha Mohan v. State of Kerala
Case brief
What is this about?
In this writ petition challenging delay regarding an earth removal application for the Kerala State Transport Project, the court directed the Chief Engineer to consider and pass orders within four weeks after hearing the petitioner.
What did the court decide?
Directed the 1st respondent (Chief Engineer) to consider and pass orders on the Ext.P6 application within four weeks after hearing the petitioner.