Rds Project Ltd. v. Central Public Works Department(Cpwd)
Case brief
What is this about?
This writ petition sought payment of a construction bill. The court held that the Central Public Works Department must hear both parties regarding final settlement and rectification work within three weeks and release the balance amount within three weeks thereafter, rather than issuing an immediate payment order.
What did the court decide?
Directed CPWD to hear parties on settlement within 3 weeks and pay due amount within 3 weeks of such hearing.