blocks had to be constructed viz., A, B, C and D. However, as on the date of the termination of the work, the appellant has completed only 35% of the entire work and on considering the works of blocks A and B, it would be 40%. Thus, according to the 3rd respondent, the progress of the project was very poor, which was admitted by the appellant. That apart it was contended that in spite of clause 25 of the general conditions of contract for constitution of dispute redressal committee, the 3rd respondent had the power to terminate the work by virtue of clause 3 of the general conditions of contract. It was also submitted that the issues raised by the appellant in Exhibit P10 request would not come under clause 25 of the general conditions of contract in order to refer the same to the Disputes Redressal Forum, apart from stating that the disputes, if any, has to be raised within 15 days of the same and none of the matters contained in Exhibit P10 request arose within 15 days as on the date of Exhibit P10 request. It was also pointed out that, taking into account the flood situations and COVID-19 pandemic, Exhibit P6 supplementary agreement was executed on 24.9.2020 extending the period of completion of work upto 28.2.2021 and thereby, increasing the period from 730 days to 949 days. Thus, according to the 3rd