Hydro Electrical System v. Kerala Water Authority
Case brief
What is this about?
In this petition, the petitioner, a contractor, sought writ relief for non-payment of bills regarding modernisation of a pumping station. The respondent counsel agreed to pay within four months, leading the court to dispose of the petition with a direction to make payment accordingly.
What did the court decide?
Direction given to the respondents to make payment within four months in accordance with priority.