Radhakrishnan O., v. State of Kerala
Case brief
What is this about?
In this writ petition, the petitioner, a contractor who completed specified works under a personal agreement, sought approval of his final bill. The court directed the respondents to make the payment due under the Ext.P1 and Ext.P2 agreements within two months, holding that the petitioner is not personally liable for penalties imposed on the principal contractor. The petition was disposed of by gr
What did the court decide?
Direction to respondents to make the payment due to petitioner on basis of Ext.P1 agreement and Ext.P2 bill within two months from date of receipt of copy of judgment.