H.Dileep Kumar v. the Secretary of Industry Department
Case brief
What is this about?
Petitioner, a contractor, approached the Court for payment of a final bill for street lighting works executed for Kerala Government entities. The respondents delayed payment citing variations and lack of approval. The Court found the work completed and material substitution approved, directing payment of the balance amount.
What did the court decide?
Respondents directed to process the final bill within four weeks and pay the balance amount within a further four weeks.