to the complaint of the local people that there is water logging during rainy season, Municipality has decided to construct a drainage in order to alleviate the said problem. The total length of the proposed drainage is 298 metres. Accordingly, an estimate of Rs.35 lakhs for construction of a drainage was prepared. Due to paucity of funds, it was decided to complete the work in two phases and an amount of Rs.14,44,000/- was earmarked in the year 2013-14 for starting the work. Technical sanction was also obtained as per Communication No.474(a)/AEE/EBP/13-14 for the said work. Along with the other works, steps were taken for inviting tenders from suitable persons. In the meantime, Lok Sabha election was declared and hence, further proceedings in respect of the said work was temporarily stopped. It is further stated that after the election, Municipality invited tenders in respect of the said work and completed the first phase, in a time bound manner. As far as the second phase of the work is concerned, no fund has been allotted. However, it is stated that the same would be completed on receipt of funds without further delay. It is finally contended that there is no direction to the Municipality as per the judgment dated 20.03.2013, to complete the work in a time bound manner and, therefore, they have not committed any contempt of court.