Shaji Mathew, v. the Chief Engineer
Case brief
What is this about?
In this writ petition, the petitioner, a contractor, sought issuance of a Completion Certificate which was not granted, preventing bill settlement. The High Court directed the Chief Engineer to secure government approval within a month and direct the Executive Engineer to consider the completion certificate request.
What did the court decide?
Direction to the 1st respondent to secure Government approval within one month and the 2nd respondent to consider the Completion Certificate request thereafter.