Abdul Nazar P. v. the Superintending Engineer
Case brief
What is this about?
High Court directed respondents to adjust 50% of the security deposit and performance guarantee from the pending bill amount as per Ext.P2, extending execution timeline by two weeks.
What did the court decide?
Direction to adjust 50% of security deposit and performance guarantee from pending bill amount; extension of execution period by two weeks.