Fakrudheen Ali Ahammed U v. the Chairman and Managing Director
Case brief
What is this about?
The High Court of Kerala disposed of a writ petition where a contractor challenged non-payment for satisfactorily executed cable work. The Court directed Bharat Sanchar Nigam Limited to pay the admitted balance amount within three months, with 50% due in 45 days.
What did the court decide?
Directed the concerned respondent to effect the balance payment within three months, with 50% payable within 45 days of receipt of the judgment copy.