Lurdh Matha Constructions v. the Superintending Engineer
Case brief
What is this about?
Petitioners in a construction contract sought relief for delays attributed to the department. The High Court held that contractual issues regarding liability and rate revisions cannot be adjudicated via writ proceedings under Article 226 and dismissed the petition without merits, directing them to civil courts.
What did the court decide?
The writ petition was dismissed as it concerned contractual disputes requiring adjudication in a civil court.