Haridasan. K v. the Assistant Executive Engineer
Case brief
What is this about?
The High Court disposed of two writ petitions regarding a dispute over electric line installation. The court found that routine assessments by village officials satisfied the objection regarding road usage. It directed the board to provide power within two weeks following the approved route, ensuring no hindrance to vehicular traffic.
What did the court decide?
Liberty to draw the electrical line through the permitted route and a direction to provide power connection to the residence of the petitioner in WP(C) No.3732/2017 within two weeks.