N.Kamalam v. District Collector
Case brief
What is this about?
The court directed the respondent-Arbitrator to pass an award in pending land acquisition compensation proceedings under Section 3G(5) of the National Highway Act, 1956, within 4 weeks after affording a reasonable opportunity of being heard to the petitioners.
What did the court decide?
Directed the respondent-Arbitrator to pass the award in the arbitration proceedings within 4 weeks after hearing the petitioners.