Pmr Construction Company v. the Superintending Engineer
Case brief
What is this about?
The Court disposed of writ petitions challenging the rejection of bid submissions for a public work contract. Recognizing the urgent nature of the work, the Court concluded that re-tendering would not prejudice any party and served the public interest.
What did the court decide?
Writ petitions closed; proposal to re-tender the work recorded; parties directed to participate in re-tender.