other contentions, it is stated that, as per AnnexureR3(a) interim order dated 21.01.2010, it was directed that a prior approval from the revenue authorities are mandatory to grant any building permit or to carry out construction of any building in Munnar area. Thereafter, the District Collector, Idukki has issued a Circular dated 09.06.2016, evident from Ext.R3(b), issuing necessary directions on account of the directions issued by the Division Bench of this Court. However, without referring to these orders, the application for building permit submitted by the petitioner was allowed by the Secretary of the Panchayat. Thereafter, the Additional Chief Secretary, by an order dated 15.02.2018, referring to the recommendation of the Vigilance Department, directed that, if any permit is issued without securing no objection from the District Collector, the same shall be cancelled.