months. No reason which would appeal to a reasonable mind has been stated by the petitioner for his failure to carry out the work within the time specified in the contract. The contract also stands terminated by Exhibit P3. In the absence of any valid ground of challenge to Exhibit P3, this Court is unable to sustain the challenge against the same. In the above view of the matter, the further contention of the petitioner that he will complete the work, if he is given 15 days further time does not require consideration especially in view of the fact that the local residents have come before this Court seeking an early resolution of the issue and for appropriate steps to be taken by the respondents for completing the work at the earliest. In the above view of the matter, the writ petition is dismissed. There will be a direction to the official respondents to see that the work is re-tendered at the earliest and completed without further delay.