R.Anantha Narayanan v. State of Kerala
Case brief
What is this about?
A contractor filed a writ petition concerning delay in receiving admitted payments for work executed under the Kuttanad Package. The Court held that paucity of funds is not a valid reason for indefinite delay, directing respondent authorities to disburse 50% by September 30, 2017, and the balance by November 15, 2017.
What did the court decide?
Directing respondents to disburse 50% of admitted dues by 30.09.2017 and the balance by 15.11.2017.