N.T.P.C.Ltd v. M/S.Reshmi Constructions
Case brief
What is this about?
Construction arbitration concerned delay, extra work and disputed final settlement. The court applied the Arbitration Act, 1940, modified the award by confining compensation to the compromise bill with 12% interest, and held that conditional withdrawal against security did not stop interest. Both appeals were allowed, with expedited disbursement directed.
What did the court decide?
Award modified to compensation under the compromise bill with 12% interest until payment; immediate partial disbursement and payment of the balance within two weeks directed.