Jabeena Abraham v. State of Kerala
Case brief
What is this about?
The Court held that although land acquisition for the Kochi Metro Project occurred after the 2013 Act, the award was passed under the 1894 Act. Disposing of the writ petition, the Court directed the respondents to re-determine the compensation under the 2013 Act and pay the petitioner within four months.
What did the court decide?
Direction to the respondents to re-determine the compensation payable to the petitioner under the 2013 Act and disburse the same within four months from the date of the order.