Sri.K.Udayakumar v. the Assistant Executive Engineer
Case brief
What is this about?
The petitioner challenged the State Electricity Board's short assessment bill arguing he was a subsequent owner with a lower connectivity. The court upheld the Ombudsman's confirmation of the demand, granting two months to pay the balance without immediate interest, threatening 6% annual interest for delayed payment. Dismissal of writ petition with directions.
What did the court decide?
Challenge to Ombudsman orders negatived; petitioner granted two months to remit balance amount without interest; default interest of 6% per annum to accrue if not paid within the period.