Faizal K M v. Assistant Executive Engineer
Case brief
What is this about?
The court disposed of a writ petition filed by an apartment purchaser claiming denial of individual electricity connection. The court directed the builder to take steps to obtain a building connection within three months, warned of disconnection if failed, and kept the specific claim open.
What did the court decide?
Direction to the builder (Additional 2nd Respondent) to obtain power connection within three months; warning of disconnection if failed; claim kept open pending builder's action.