M/S.Neel Under Water Services v. K.S.E.B.
Case brief
What is this about?
In a second appeal arising from a contract dispute over underwater plugging work at Malampuzha Dam, the Kerala High Court set aside lower court orders dismissing the plaintiff's claim. The Court held that statutory requirements for extra work were met, making the defendants liable to pay additional costs incurred to make the main work executable, relying on Section 70 of the Indian Contract Act.
What did the court decide?
Impugned judgments and decrees set aside; original suit decreed allowing the appellant to realize Rs.57,940/- with 6% interest from the trial court decree date.