Case brief
What is this about?
The Court held that the petitioner society is entitled to a proportionate reduction in the demanded arrears for the period between June 20 and September 29, 2000, during which it could not remove sand due to a stay order, without allowing a refund of amount already paid.
What did the court decide?
The demand for arrears made under Exhibits P13 and P15 is directed to be reduced proportionately for the period between 20.06.2000 and 29.09.2000.