Petitioner is a PWD contractor, who has approached this Court challenging Exts.P8 and P10, by which the 1st respondent took a decision to re-tender the work which was originally allotted in his favour. The facts involved in the writ petition would disclose that the work relating to the patch work of Puthiyaparamba - Poothapara road under the Peoples Planning Scheme of Kannur District Panchayat was originally awarded in favour of the petitioner. According to him, he had done a portion of the work, but on account of severe rain, the balance work could not be completed. The work order was cancelled at the risk and cost of the petitioner and it was decided to re-tender the work in terms of Ext.P8 dated 01/10/2011. According to the petitioner, he was not responsible for the delay in doing the work and therefore the termination order is bad in law. It is further contended that no steps could be taken to recover any loss from the petitioner and the cancellation of the work order at his risk and cost is not sustainable. Petitioner issued Ext.P9 reply dated 24/10/2011.