In such circumstances, Ext.P8 shall be considered and the measurement taken of the work already completed and the petitioner shall be paid the amounts for the work completed and the materials stored in the area, after due notice to the petitioner. It is made clear that the demolition made by the Forest Department or the stoppage of the work shall not deter the first respondent from considering such payments, since the petitioner is declared to have not committed any default in so far as the work is concerned, nor was it abandoned by the petitioner, on his own volition. The stoppage of the work was caused only due to the intervention of the Forest Department, for which the petitioner is not responsible, since the petitioner admittedly had carried on the work as per the plan and estimate given by the PWD. Ext.P8 shall be considered and payments made at any rate within a period of three months from the date of receipt of a certified copy of this judgment. The petitioner also shall not be liable for any penalty, for reason only of retendering, since the