M/S.Saurashtra Cement Ltd. v. the Chief Engineering, Department of
Case brief
What is this about?
The Kerala High Court dismissed the writ petition challenging the cancellation of a BOT agreement for a cement unit and captive jetty. The court upheld the State Government's decision, citing the petitioner's gross delay in commencing construction and obtaining necessary environmental clearances over fifteen years, rendering the agreement nugatory under its terms.
What did the court decide?
The writ petition challenging the cancellation of the BOT agreement was dismissed, and the impugned order setting aside the agreement was upheld.