for carrying out the work for several times, the petitioner did not take any earnest effort to see that the work is commenced and completed which has caused much loss and hardship to the respondents. The petitioner also did not fulfil the contractual obligation by submitting Bank Guarantee to the extent of Rs.27,68,733.89 towards balance Security Deposit/Performance Security and has failed to obtain Contractor's All Risk Insurance Policy. It was after giving several opportunities to the petitioner, that the second respondent was constrained to terminate the contract by issuing Ext.P5 order. It is pointed out that after the termination of the contract as per Ext.P5, the petitioner submitted Annexure B letter dated 29/04/2013 raising some wild allegations, which in turn was replied by the respondents, as borne by the contents of Annexure A letter. The averment of the petitioner that there was no access to the site is also pointed out as not correct, as multiple access to the site was always available to the petitioner and it was very much known to the petitioner, who made use of the same by bringing two containers to the site office . It is further pointed out that the plea raised by the petitioner as to the alleged lapse