The petitioner contractor sought recovery of pending dues for completed electrification works. The High Court directed the executing authority to disburse the amount within eight weeks after the judgment.
What did the court decide?
Direction to the third respondent to disburse the due amount under the exhibit bill within eight weeks of the judgment date.