The petitioner's father, who is no more, was a contractor, to whom, the work of widening of Mullassery canal in Ernakulam city for preventing water logging at Karikkamuri, KSRTC bus stand area, was awarded. He did not complete the work. According to the petitioner, his father could not complete the work because of obstructions for the work caused by various circumstances. According to him, electricity posts, telephone posts, cables, pipelines, sewage lines, etc. were to be removed, which were not removed and that is why his father could not complete the work. Later on, the award was cancelled and the work was got done by another contractor, by Ext.P6. The petitioner's father was directed to pay damages amounting to 47,91,083/-. After deducting the security amount and the amount for the work done by him, 44,02,811/- was directed to be paid by the petitioner's father by Ext.P7. After the death of his father, the petitioner was directed to pay the amount, failing which, destraint action was proposed. It is under the above circumstances, the petitioner has filed this writ petition seeking the following relief: