24.11.1995, which is Ext.P5. The petitioner alleges that the entire work for giving electric connection to the petitioner was over in 1996 itself but, supply was delayed without any justification and finally, he was granted electric connection only on 1.1.1997. But, according to him, the petitioner started commercial production before the said date using a generator set installed by him, having a capacity of 62.5 KVA. Since the petitioner was not given electric connection before 31.12.1996, he submitted Exts.P8 and P9 representations and also filed O.P.19444/2001 praying for the issue of appropriate directions from this Court, commanding the respondents to collect only the pre 1992 tariff rates from the petitioner. During the pendency of the said Original Petition a bill for Rs.75,095/- was issued to the petitioner which was also challenged by him before this Court in a Miscellaneous Petition filed in the writ petition referred to above. This Court had granted an order of interim stay conditional on payment of an amount of Rs.35,000/-. Subsequently the original petition was disposed of as per Ext.P11 judgment directing the Deputy Chief Engineer, KSEB to consider and dispose of the representations of the petitioner within a period of three months of the date thereof.