Petitioner is challenging recovery proceedings for recovery of compensation towards loss sustained by the Government on account of petitioner's failure to complete the construction of the road for which he was given an advance of Rs. 1.44 lakhs. Road project was under the Tribal Development Scheme at Attappady. Even though petitioner, as convenor of a committee, was awarded the work, petitioner did not complete the work and therefore entire advance was sought to be recovered with interest. Petitioner deposited Rs. 50,000/- under interim orders of this Court. The work was awarded in 1996 and obviously it was not completed within the time granted. However, strangely even after cancellation of the award of work to the petitioner, respondents have not cared to get the work completed. In the circumstances, I feel, petitioner can be granted further three months' time from today to complete the project as he has undertaken in Court to complete the work . I make it clear that time is granted on condition that petitioner