Phosphorous and Chemicals Travancore Ltd. v. Kerala State Electricity Board
Case brief
What is this about?
In a review petition regarding electricity supply demands, the Court held that the main ground concerning a rebate clause was not tenable. However, the Court observed that the quantum of demand was challengeable via appeal. It disposed of the review by directing the third respondent to revise demands after the petitioner furnishes specific defects within two weeks.
What did the court decide?
The review petition was disposed of with a direction to the third respondent to reconsider demands based on the agreement, after the petitioner furnishes specific defects in the current demand.