Sri. K Jagadish v. Bangalore Development Authority
Case brief
What is this about?
Section 38D Bengaluru Development Authority Act 1976; BDA demolition of construction on acquired land Sy. No.128 Banaswadi Village K.R. Puram Hobli; quashing of notice BDA/LAO/254/2025-26 dated 13.10.2025 Annexure-H; Articles 226/227 certiorari mandamus; interim bar on precipitative BDA action and on further construction; three-month timeline to decide regularisation application; compensation Rs. 10,00,000 sought not awarded; writ petition disposed; Karnataka HC; R. Nataraj J.; 07.07.2026.
What did the court decide?
Petition disposed of: petitioner directed to pursue Section 38D BDA Act application (dated 04.05.2026); respondent No.1 to decide it in accordance with law subject to statutory limitation within three months; interim status quo imposed — no precipitative action by respondents and no further construction by petitioner. Prayer for quashing the notice and for compensation of Rs. 10,00,000/- not decided/adjudicated.