Case brief
What is this about?
Retrospective or notional promotion from the date of promotion of junior; deemed promotion with consequential benefits despite retirement; denial of promotion not due to employee's fault; consent in review application before CAT bars writ challenge; non-implementation of Tribunal order; CAT Bengaluru O.A. No. 432/2005 and RA No.9/2011; Railway Section Engineer promotion procedure under paragraph-4 of RBE 5/04 dated 6.1.04; South Western Railway; writ petition under Articles 226/227 rejected with two months' compliance time; NC: 2026:KHC:76-DB; S-CAT; High Court of Karnataka.
What did the court decide?
Writ petition rejected; petitioners granted two months' time from the date of the order to comply with the Tribunal's order (promotion of respondent No.1 from the date his next junior was promoted, with consequential benefits); pending I.A.s, if any, stand disposed of.