M/S Yojaka (India) Pvt. Ltd. v. the Executive Engineer
Case brief
What is this about?
Petitioner challenged cancellation and EMD forfeiture of a dredging tender. Respondent cited lack of central funding shelving the project. Court held respondent cannot retain EMD if no work proceeds, set aside forfeiture, ordered refund, but upheld tender cancellation.
What did the court decide?
Writ petition partly allowed; cancellation upheld; EMD forfeiture set aside; refund of EMD directed.