M/S Gita Refractories Pvt. Ltd. v. State Bank of India
Case brief
What is this about?
The petitioner, an MSME, challenged the State Bank of India's unilateral insertion of a one-year claim period beyond the validity period stipulated in the purchase order and the bank guarantee application. The bank relied on Exception 3 to Section 28 of the Indian Contract Act and a banking circular to justify the extension. The High Court, following a Delhi High Court decision, held that Exception 3 does not impose a mandatory minimum claim period and that the bank cannot unilaterally enlarge the petitioner's obligations. The writ petition was allowed, setting aside the extended claim period and directing the bank to honour the guarantee as per the originally agreed terms.
What did the court decide?
The stipulation providing a claim period up to 21.04.2023 is set aside; respondent No.1 shall give effect to the Advance Bank Guarantee in accordance with the terms and period originally agreed.