Upper Krishna Project; Alamatti Dam submergence; FRL 519.60 to 524.256; consent award; land acquisition compensation delay; Karnataka HC Dharwad bench; Lalitha Kanneganti J.; Government Order No. JASUME 93 KBN 2025 dated 09.10.2025; final notification s.19(1) dated 13.11.2022; preliminary notification s.11(1); SLAO consent award; KBJNL; UKP Commissioner; Bennur; Govindakoppa; Mugulloli; Udagatti; Kirasur/Kerasur; Machakanur; Yenkanchi; Korti; Bagalkot; writ petitions under Articles 226 and 227; award deadline 16.08.2026; payment deadline 16.10.2026; contempt proceedings partial payments; affidavit Regional Commissioner Belagavi Division dated 16.02.2026; memo for being spoken to; oral order 26.02.2026.
What did the court decide?
Direction to all respondents to pass the award by 16.08.2026 and to pay the compensation amount as per the award to the land losers by 16.10.2026; copy of the order to be communicated to respondent Nos.1, 2, 4 and 5; all pending I.As. closed; supplementary oral order dated 26.02.2026 incorporating a village-wise table of preliminary (u/s 11(1)) and final (u/s 19(1)) notifications and SLAO order numbers, to be read as part and parcel of the final order dated 17.02.2026.