Nandi Infrastructure Corridor Enterprise Limited v. Smt. Rathna S. Reddy
Case brief
What is this about?
BMICP land acquisition quashed; KIAD Act Section 28(1) preliminary notification 14.06.2006; Section 28(4) final notification 16.10.2008; no award passed; no compensation paid for 17 years; Nandi Infrastructure Corridor Enterprise Ltd (NICE) writ appeal dismissed; Karnataka High Court Act Section 4; WP No. 20824/2025 (LA-KIADB) Single Judge order dated 05.12.2025 upheld; Sy No.41/5 not required for BMICP; no ramp, interchange, link alignment or BMICP facility; BMICP Area Planning Authority endorsement 05.06.2025; State affidavit in Supreme Court Contempt Petition (C) No.139/2012 — 554 acres excess land already handed over; Article 300A right to property constitutional right; deprivation without due compensation; bench D K Singh and S Rachaiah; judgment dated 24.02.2026.
What did the court decide?
None; the writ appeal was dismissed and the learned Single Judge's order quashing the land acquisition proceedings in respect of the petitioner's land stands.