The Excutive Engineer v. Chandramma
Case brief
What is this about?
Karnataka High Court, Bengaluru; WA No. 630 of 2026 (GM-KEB); decided 10 July 2026; coram D K Singh and T.M. Nadaf, JJ. KPTCL Executive Engineer and Assistant Executive Engineer (Chitradurga) challenged Single Judge's order dated 12.11.2025 in W.P.No.32251/2024 upholding enhancement of compensation for a high voltage 220 kilowatts power line corridor over respondent Chandramma's line: Deputy Commissioner had fixed Rs.2,08,924/-; Principal District and Sessions Judge (Misc.No.352/2022, order dated 14.08.2024) enhanced by Rs.27,495/- with 8% interest per annum; Single Judge relied on Executive Engineer and Another Vs. Doddakka, W.P.No.39979/2013 dt. 06.08.2014. Appeal dismissed; interim deposit payable to respondent with accrued interest; shortfall to be made good within four weeks. Filed under Section 4, Karnataka High Court Act, 1961.
What did the court decide?
No relief to the appellants; writ appeal dismissed. The amount deposited pursuant to the interim order, with accrued interest if any, is to be paid to the respondent on proper verification, and any shortfall from the amount determined by the Principal District and Sessions Judge is to be made good within four weeks.