Sri B S Suresh, v. the Chief Commissioner
Case brief
What is this about?
Keywords: writ appeal dismissed; intra-court appeal; S.4 Karnataka High Court Act; BBMP; BESCOM; BWSSB; additional/unauthorised construction; violation of interim order dated 01.09.2025; conditional restoration of electricity; CCTV monitoring of construction site; restraint on occupation; restraint on electricity and water connections; W.P.No.123/2026; W.P.No.26450/2025; W.P.No.26540/2025; order dated 07.07.2025 of Assistant Executive Engineer; Bengaluru; LB-BMP; no costs discussed; no precedent relied upon.
What did the court decide?
None. The writ appeal is dismissed; parties may agitate their rights before the learned Single Judge in the pending W.P.No.123/2026, and pending interim applications, if any, stand rejected as not surviving for consideration. ¶78