Karnataka HC Dharwad review petition allowed 09.02.2026 (Justice G Basavaraja); RP No.100101/2025 c/w RP No.100103/2025 by M/s Pradeep Construction Company vs Belagavi Smart City Ltd MD, Secretary UDD GoK, Executive Engineer BSCL; review of orders dated 07.08.2025 in CMP No.100016/2024 and CMP No.100017/2024 that appointed respondent No.2 (Secretary, UDD) as Arbitrator; impartiality/independence objection under Section 12(5) Arbitration and Conciliation Act 1996; reliance on Central Organization for Railway Electrification v. ECI SPIC SMO MCML (JV) 2024 INSC 857; new Arbitrator appointed: Sri Virupakshaiah H.M., Former District Judge; agreements dated 30.07.2019 and 12.07.2019; Arbitration Center Bengaluru.
What did the court decide?
Review allowed; Sri Virupakshaiah H.M., Former District Judge, appointed as Arbitrator (replacing respondent No.2) in terms of the agreements dated 30.07.2019 and 12.07.2019; copy of the order with the agreements to be sent to the Arbitration Center, Bengaluru for necessary action.