Sri a C Venkatesh v. National Highways Authority of India
Case brief
What is this about?
Condonation of delay 1162 days dismissed; MFA under S.37(1)(c)/Section 37 Arbitration and Conciliation Act 1996; appeal against District Judge order of 14.10.2022 in A.P.No.77/2020 allowing NHAI's Section 34(2) petition setting aside arbitral award dated 09.07.2019; NHAI land acquisition compensation, final notification 14.08.2006, Hyderabad-Bengaluru Section NH-7, Avathi Village Devanahalli Taluk Bengaluru Rural District; sufficient cause; Section 5 Limitation Act; Articles 116/117 Limitation Act; Section 13(1-A) Commercial Courts Act; State of MP v. Ramkumar Choudhary 2024 SCC OnLine SC 3612; Govt. of Maharashtra v. Borse Brothers (2021) 6 SCC 460; Esha Bhattacharjee (2013) 12 SCC 649; Kumbhakarna; casual approach, no diligence; appeal dismissed; High Court of Karnataka; Pradeep Singh Yerur J.; decided 02.07.2026.
What did the court decide?
An appeal under Section 37 of the Arbitration Act must be filed within the prescribed time limit; delay can be condoned only where the Court is satisfied with sufficient cause and cogent reasons which are not negligent or deliberate, and with an admitted delay of 1162 days the onus lay heavily on the appellant to explain.