State Project Director, v. M/S. Bsr Infratech India Ltd.
Case brief
What is this about?
The High Court of Karnataka allowed a commercial appeal under Section 13(1A) of the Commercial Courts Act, 2015 read with Section 37(1)(c) of the Arbitration and Conciliation Act, 1996, setting aside the arbitral award in respect of Claim Nos. 7(a) (unproductive overhead charges), 8 (loss of expected profit), and 12 (costs). The Commercial Court had upheld the award. The High Court held that the award for unproductive overheads was unsustainable because the claimant made no averments or led evidence to justify it, and the tribunal applied the Hudson Formula suo motu. The award for loss of profit was unsustainable because the contract was fully performed and the contractor had realized the contracted profit; the tribunal awarded 10% per annum of assured profits without any basis. Consequent
What did the court decide?
The arbitral award dated 10.11.2023 is set aside insofar as it awards Claim No.7(a) (Rs.1,59,75,852/-), Claim No.8 (Rs.90,52,982/-), Claim No.12 (Rs.2,00,000/-) and future interest at 9% per annum thereon.