State Project Director, v. M/S. Bsr Infratech India Ltd.
Case brief
What is this about?
The High Court allowed an appeal under Section 37(1)(c) of the Arbitration and Conciliation Act, 1996, setting aside an arbitral award that granted unproductive overhead charges, loss of profit, and costs to the contractor. The Court found no basis for the Hudson Formula application or the 10% profit assumption, and held the cost award fell with the main claims.
What did the court decide?
Impugned award set aside insofar as it awards Claim Nos.7(a), 8 and 12 and interest thereon.