Sri N P Diwakar Seth v. the Special Land Acquisition Office
Case brief
What is this about?
Karnataka High Court; Justice M.Nagaprasanna; writ petition rejected; land acquisition lapse; re-conveyance claim resting on CITB resolution/communication dated 04.08.1965; delay and laches; representations do not obviate delay or arrest time; delay defeats equity; law protects the diligent not the indolent; MUDA (then CITB) Mysuru; Sy.Nos.209 and 210, Mananavadi Road, Mysuru Kasaba Village; preliminary notification 17.01.1962; award 12.05.1964; endorsement dated 21.11.2016; Articles 226 and 227 of the Constitution of India; Urban Development Authorities Act; LA-UDA.
What did the court decide?
Mere submission of representations will not obviate delay and arrest time; delay defeats equity as well, and the equity that once stood with the petitioner's father or the petitioner has vanished on sheer negligence, the petition hinging on representations all submitted with gross delay.