M/S. Hdb Financial Services Ltd. v. M/S. Renown Hotels and Resorts Pvt. Ltd.
Constitution of India, Article 227 – CPC, Order VIII Rule 1 – Written statement beyond 90 days – Condomation of delay
Case brief
What is this about?
HDB Financial Services Ltd. v. Renown Hotels & Resorts Pvt. Ltd.; Writ Petition No.8181 of 2021 (GM-CPC); High Court of Karnataka, Dr. Justice K. Manmadha Rao, decided 16.09.2025 (rectified 05.12.2025); Article 227 writ against trial court order refusing to take written statement on record; Order VIII Rule 1 CPC 90-day limit held directory not mandatory; condonation of delay of 490 days; Section 151 CPC applications; cost Rs.10,000/-; underlying suit O.S.No.3601/2018 for refund of foreclosure/pre-closure charges of Rs. 9.03,246.61/-; Banking Ombudsman Scheme 2006 clause 3(5); loans of Rs. 3 Crores and Rs. 20 Lakhs; Supreme Court precedents Rani Kusum v. Kanchan Devi, Zolba v. Keshao, Atcom Technologies Ltd. v. Y.A. Chunawala & Co., Sailendra Kumar Sisodia v. Rani Sisodiya.
What did the court decide?
Writ petition allowed: order dated 23.03.2021 in I.A.No.2 set aside; trial Court to receive the defendants' written statement and dispose of O.S.No.3601/2018 as expeditiously as possible, within eight months from receipt of the order; both parties to co-operate; cost of Rs.10,000/- (recorded as already deposited vide Demand Draft No.032616 dated 04.05.2021) to be transmitted to the trial Court.